Coal to Bishkek HPP to be delivered behind schedule, because contract with supplier is not concluded

20:42, 19 May 2014, Bishkek - 24.kg news agency
Julia KOSTENKO

Coal to Bishkek HPP will be delivered behind schedule, because the contract with supplier hasn\'t been concluded,\" the Electrical Stations OJSC reports.

 

It is noted that the tender committee recommended concluding contract for the supply of 630,000 tones of Kazakh coal with Progress Company LLC which estimated fuel at $35,884,800. Currently an audit report is being prepared, after learning that the procuring entity will make a decision. It is expected that it will be ready this week.

 

According to the Electrical Stations, according to the schedule the first 30,000 tons metropolitan heating plant should have arrived in early May. However, due to the fact that the contract is not concluded, the delivery schedule will be postponed.

 

The Electrical Stations allocated 1,559.25 billion soms for fuel purchasing. Long- and coal gas belongs to the category of high-energy fuel, produced from the coal fields of Kazakhstan. In the experience of many years in Bishkek HPP receives shabyrkul fuel.

 

It should be noted that the procuring entity has no money for coal procurement. Electrical Stations refused from electricity exports because of the low volume of water in the Toktogul reservoir. Previously coal, oil and gas were bought on the proceeds. This year power engineers hope to get loans from international banks and low cost loans to cover the current deficit.

 

 

CONTACTS

SOCIAL MEDIA

TelegramYouTubeWhatsAppFacebookInstagram

© News Agency «24.kg» - News of Kyrgyzstan. All rights reserved. All information posted on this website is intended for personal use only and may not be distributed without the written permission of NA «24.kg». The editorial team is not responsible for the content of reprinted materials and statements of individuals. +18