Chorobai Akunov: Preparatory works for Verkhnenaryn HPP cascade construction are ahead of schedule
\"For preparatory works for the beginning of Verkhnenaryn HPP (hydro power plant) cascade construction 2 years were given, but we are ahead of the schedule,\" the member of the board of Verkhnenaryn HPP CJSC Chorobai Akunov said at the media tour.
According to him, the preparatory work started in May 2013, and in September 2014 it will be possible to start the main construction works for hydroelectric power plants.
According to the member of the Board, today shift camp for 2,100 people is completed as well as chink for water, gravel plot, concrete plant and road. Field camp is equipped with boiler, which provides building for heat and hot water, paved central drainage, built club, cinema, shop, medical center.
As the organizers of the tour noted, the sewage system in the village eliminates dumping in the Naryn River.
Recall, Verkhnenaryn HPP cascade includes four hydroelectric power plants in the upper Naryn River. Construction started in 2013 and will be completed in 2019. The Russian side is financing the construction totaling $727 million.