Transit of electricity from Uzbekistan to Kyrgyzstan to continue until construction of Datka-Kemin second line
The transit of electricity from Uzbekistan to Kyrgyzstan will continue until the second line of Datka-Kemin to be built,\" the Head of Datka Substation Abdumitalip Eshmambetov said to journalists.
According to him, currently, substation fully provides electricity in Osh region. \"The station was built over a year ago, and the project cost $208 million, Datka - $56 million. The total length of transmission line - 76 km,\" he said.
He added that now Datka power line pumps electricity from Uzbekistan and Kazakhstan up to 40 percent of the total power. \"Once Datka-Kemin project finishes completely, the country\'s energy security will be ensured,\" Abdumitalip Eshmambetov concluded.