About 7,351.6 soms allocated for reconstruction of Osh TPP
About 7,351.6 soms were allocated for reconstruction of Osh Thermal Power Plant, the website of public procurements informed.
It is noted that the Electrical Stations OJSC, subsidiary of which TPP is, intends to install a pipeline network to replace the pipes, auxiliary facilities and repair service and maintenance operations.
Work is planned for the second quarter of 2014 for main heating system of 600 meters length on Abdykadyrov Street. Overhaul of auxiliary equipment of the boiler and reconstruction of district heating network Osh is planned.
Opening of tenders will take place on May 30.