Kyrgyzstan provides for 29,285,770 soms for hydropower plants repairing
Almost 29,285,770 soms are allocated for the repairing of hydropower plants (HPP) of Kyrgyzstan. The official portal of the state procurements informs.
It is noted that allocated means will be spent for overhaul repairs of hydraulic unit number 3 of Uch-Kurgan HPP, hydraulic unit number 1 of At-Bashy HPP, hydraulic unit number 1 of Tash-Kumyr HPP, medium repairs of hydraulic turbine number 4 of Toktogul HPP. The works are scheduled for May-August of 2014. Applications are accepted until March 28.
In addition to it Electric Stations OJSC intends to carry out repair works of HPP equipment at 11,709,470 soms. Opening of tenders will take place on April 2.