Construction works suspended at 500kW Datka-Kemin power transmission line
Construction works at 500kW Datka-Kemin power transmission line were suspended. The Director General of the National Electric Network of Kyrgyzstan Company Medetbek Aitkulov informed today at the meeting with journalists.
According to him, the works were stopped because of bad weather. Besides, China celebrates the New Year. In regard to it Chinese contractors organized short vacations. \"The line runs in difficult mountain area. The Chinese say that it is the most complicated line in the world. Works at Kemin substation are also suspended,\" Medetbek Aitkulov explained.
He noted that the construction works will be resumed in mid-February. \"At present the equipment is supplied by 95 percent. Works on concrete casting of foundation are 70 percent completed. Erecting of supports has already begun. We will start mounting wires of the line in spring. Besides, we asked the contractors to finish the works at Kemin substation this year, although the deadline, determined in the contract is August 30, 2015,\" Medetbek Aitkulov said.