At this rate, introduction of the automated electricity metering control system in Kyrgyzstan will take 26 years. Deputy Ekmat Baybakpaev made such a conclusion at the meeting of the Committee on Fuel and Energy Complex and Subsoil Use.
He said that smart meters are installed very slowly.
"We will install them 20-26 years. Only 3,000 meters such meters were installed in Osh," the deputy said.
In his opinion, it is sabotage.
Ekmat Baybakpaev added that Severelectro JSC spent on the equipment more than $ 6 million.
However, this equipment is in warehouse and is not used.